Pathworks Engineering
← Back to workEnergy & Renewables

Solar-plus-battery energy storage system design

An industrial owner, developer and microgrid integrator serving a Southern California industrial campus with a constrained utility export limit.

Solar-plus-battery energy storage system design
Input received
Interval load data, tariff and demand-charge structure, PV production model and loss budget, the site plan and fire-access constraints, and battery/PCS/transformer vendor data with the utility interconnection agreement.
Delivered
A PV/BESS sizing report and interval dispatch workbook, battery-block and PCS/transformer/switchgear layouts, AC/DC one-lines and protection concept, EMS mode definitions, a code-compliance matrix, and a degradation/augmentation plan.
Timeline
Ten Pathworks production weeks after approved load data, tariff, site plan, utility criteria and vendor basis. Excludes AHJ, fire-authority and utility review cycles.

Dispatch assumptions are carried into an equipment-level model so a financial dispatch curve is never issued as an electrical design without a safe, traceable equipment path. The representative design combines 24.001 MWdc of single-axis tracker PV with a 10 MW BESS carrying 44 MWh usable at beginning of life against a 40 MWh guaranteed usable commitment: campus peak falls from 22.4 MW to 14.3 MW, curtailed PV drops from 7.8 GWh to 1.6 GWh, and PV capture rises from 81.8% to 96.3% (approximately 94.4% delivered after 87% round-trip efficiency).

Solar array
24 MWdc
Battery power
10 MW
Usable energy
40 MWh
Curtailment cut
79.5%

The engineering problem

The campus can host more PV than the utility export limit and daytime load can absorb, so a PV-only solution clips or curtails energy during strong solar hours while the facility still experiences a late-afternoon demand peak. The design must coordinate energy dispatch with physical battery blocks, PCS ratings, transformer loading, protection, grounding, auxiliary power, communications, fire access and vendor degradation, because a financial dispatch curve cannot be issued as an electrical design until each operating state has a safe and traceable equipment path.

Design parameters and calculation basis

PV nameplate40,680 modules × 590 W = 24.001 MWdc, single-axis tracker ground mount
PV AC12 inverter stations × 1.5 MW = 18.0 MWac
PV DC/AC24.001 ÷ 18.0 = 1.333
BESS rating10 MW discharge / 40 MWh usable; 4-hour duration
Initial energy44 MWh usable at beginning of life; ≈48.9 MWh installed nameplate at a 90% state-of-charge window
Round-trip efficiency87% AC-to-AC representative planning value
Peak result22.4 MW − 8.1 MW = 14.3 MW managed peak
Curtailment7.8 GWh − 1.6 GWh = 6.2 GWh / 79.5% reduction

Key design decisions

A four-hour BESS is selected because the peak and curtailment windows overlap for multiple hours; a one- or two-hour system cannot satisfy both objectives consistently. Four 2.5 MW PCS blocks are used so maintenance or a single-block outage does not remove all dispatch capability. Approximately 48.9 MWh of nameplate is installed to give 44 MWh usable at beginning of life, with a year-6 augmentation area reserved so the 40 MWh guaranteed usable commitment holds through year 10 under the representative degradation curve. Safety and utility export limits are prioritized above tariff dispatch in the EMS hierarchy, and UL 9540A evidence, fire access and OEM spacing are treated as design inputs rather than notes added after the block layout is frozen.

Design and quantity control

Operating measurePV onlyPV + BESSRepresentative outcome
Campus peak22.4 MW14.3 MW8.1 MW reduction
PV generation42.8 GWh42.8 GWhSame resource basis
PV curtailed7.8 GWh1.6 GWh6.2 GWh / 79.5% reduced
PV captured (before storage loss)35.0 GWh41.2 GWh81.8% → 96.3% captured; ≈94.4% delivered after 87% round-trip
Usable energy40 MWhYear-6 augmentation reserved

QA steps and evidence

QA gateAcceptance testEvidence / result
Energy balancePV, load, charge, discharge, losses and curtailment reconcile42.8 GWh PV / 1.6 GWh residual curtailment
Power balancePCS, transformer and export limits checked in every mode10 MW BESS / 12.5 MW export cap
Safety basisListing and fire-code evidence indexedUL 9540 / 9540A register
Usable energyDegradation and augmentation maintain commitment≥40 MWh through year 10
Issue controlDispatch IDs match equipment and one-line IDsFour coordinated releases

Revision record

ReleaseTriggerChange madeControlled outcome
ConceptLoad and PV time seriesSelected 10 MW / 40 MWh four-hour architecturePeak and curtailment objectives both served
30%Vendor and fire inputsReoriented blocks; added separation and accessCode pathway established
60%Utility and protection reviewUpdated transformer, metering and export controlsInterconnection basis reconciled
Issued supportWarranty and augmentation reviewReserved 4.8 MWh year-6 addition40 MWh usable commitment protected

Result and calculation trail

The representative design combines 24.001 MWdc of single-axis tracker PV with a 10 MW / 40 MWh BESS. Under the illustrative interval model, the campus peak falls from 22.4 MW to 14.3 MW, curtailed PV drops from 7.8 GWh to 1.6 GWh, and PV capture rises from 81.8% to 96.3% — approximately 94.4% delivered to load after 87% round-trip efficiency — while a year-6 augmentation preserves usable energy.

PV DC capacity: 40,680 × 590 W = 24.001 MWdc. BESS duration: 40 MWh ÷ 10 MW = 4.0 hours. Peak reduction: 22.4 − 14.3 = 8.1 MW, or 36.2%. Curtailment reduction: (7.8 − 1.6) ÷ 7.8 = 79.5%.

Pathworks developed a representative 24 MWdc solar-plus-storage design for an industrial campus with a constrained export limit; the 10 MW / 40 MWh BESS coordinates peak shaving, PV capture, safety, one-lines, protection, EMS modes and augmentation in one controlled design package.

Solar-plus-storage plant architecture from PV and BESS to utility interface
Solar-plus-storage plant architecture: the dispatch model, electrical one-line and safety basis share the same equipment identifiers, from 24 MWdc PV through the 10 MW / 40 MWh BESS to the utility interface.
Representative summer-day dispatch chart showing campus load, PV output and BESS charge/discharge
Representative summer-day dispatch: BESS charging is shown below zero and discharge above, holding the campus import to a 14.3 MW managed peak.
Usable-energy and augmentation plan over a 10-year operating horizon
Usable-energy and augmentation plan: a year-6 augmentation of 4.8 MWh holds the system at or above the 40 MWh usable commitment through year 10 under the representative degradation curve.

Have a similar project?

Send us what you have and we’ll scope it the same way.

Start a Project