Pathworks Engineering
← Back to workEnergy & Renewables

Wind-farm repowering and electrical balance-of-plant design

A wind owner/operator, developer and repowering EPC replacing an aging fleet across the Iowa / Great Plains region.

Wind-farm repowering and electrical balance-of-plant design
Input received
Existing as-builts, GIS, cable schedules and relay settings, current survey and turbine coordinates, new turbine power-curve and equipment data, and collection/substation load-flow and fault data.
Delivered
An asset-disposition register, repowered turbine/access-road/crane-pad plans, 34.5 kV collection and grounding drawings, substation-interface one-lines and equipment schedules, and demolition/cutover work packages.
Timeline
Twelve Pathworks production weeks after survey, condition, geotechnical, turbine, collection and interconnection inputs. Excludes utility, outage-approval and OEM certification cycles.

A retained/modify/replace disposition is built for every existing asset, using the same asset IDs across the turbine plan, access design, collection circuits, substation interface and demolition package. The representative full repower replaces 68 × 1.5 MW turbines with 40 × 4.2 MW units, raising capacity from 102 MW to 168 MW and net annual energy from 290 GWh to 654 GWh while retaining 65% of access alignment and 36% of trench/duct corridors.

Turbine count
68 → 40
Capacity
102 → 168 MW
Net annual energy
654 GWh
Life extension
25 years

The engineering problem

The existing plant has secured land, roads, a substation and 34.5 kV collection, but those assets were designed around smaller turbines and an older operations basis. New machines change wake spacing, foundation loads, crane logistics, feeder power, fault duty, protection, transformer loading and the location of every cable termination. Repowering value depends on disciplined reuse: existing roads, ducts, trenches, cables and substation equipment are retained only where condition, capacity, geometry and records support the new duty, since unsupported reuse transfers cost and outage risk to construction.

Design parameters and calculation basis

Existing plant68 × 1.5 MW = 102 MW
Repowered plant40 × 4.2 MW (≈150 m rotor, 100 m hub height, ≈238 W/m² specific power) = 168 MW
Capacity increase66 MW / 64.7%
Net annual energy290 GWh → 654 GWh / 125.5% increase
Collection loss2.6% → 1.7% of gross production
Collection length47.2 circuit-mi → 43.5 circuit-mi / 7.8% reduction
Reuse65% access-road alignment; 15.8 mi of the 43.5 circuit-mi repowered route / 36% trench or duct corridor
Life extension25 years projected, subject to turbine, civil and electrical certification

Key design decisions

Full repowering is used because larger rotor and hub-height gains justify fewer turbines and a renewed design life; partial component replacement does not meet the representative energy target. Road alignment is retained where geometry and drainage can be upgraded, but curves are widened and segments reinforced for the new transport envelope. Trench or duct corridors are reused only after survey, cable condition and capacity checks — a mapped route is never treated as automatically reusable electrical plant. Eight 34.5 kV feeders are rebuilt around 21 MW nominal groups to control ampacity, voltage drop, outage exposure and sectionalizing — each group draws approximately 351 A at 34.5 kV, sized on 1,000 kcmil aluminum with direct-buried derating applied — and the existing substation transformer is replaced with a 200 MVA unit with breakers, bus, protection and grounding revalidated against the new duty.

Design and quantity control

Asset / measureExistingRepoweredControlled outcome
Turbines68 × 1.5 MW40 × 4.2 MW102 → 168 MW
Net annual energy290 GWh654 GWh+364 GWh / 125.5%
Collection loss2.6%1.7%0.9 percentage-point reduction
Circuit length47.2 mi43.5 mi3.7 mi / 7.8% removed
ReuseLegacy roads / trenches65% road / 36% corridorCondition-based disposition

QA steps and evidence

QA gateAcceptance testEvidence / result
Existing recordsAsset IDs and routes reconcile to evidence284 drawings / schedules indexed
Turbine layoutOEM, property, access and wake constraints applied40 controlled positions
CollectionAmpacity, voltage drop and feeder grouping checkedEight 34.5 kV feeders
ReuseCondition and capacity disposition recorded65% road / 36% corridor reuse
Issue controlDemolition, new work and cutover agreeThree design releases + as-built conversion

Revision record

ReleaseTriggerChange madeControlled outcome
30%Record and layout reviewRemoved unsupported cable reuse; shifted seven turbine sitesControlled retained / replace basis
60%Transport and collection reviewUpgraded road curves; rebalanced eight feedersConstructable logistics and electrical plan
Issued supportSubstation and cutover reviewUpdated transformer, outage and demolition packagesRepower work packages released

Result and calculation trail

The representative full repower replaces 68 × 1.5 MW turbines with 40 × 4.2 MW units. Nameplate capacity rises from 102 MW to 168 MW, modeled net annual energy increases from 290 GWh to 654 GWh, collection losses fall from 2.6% to 1.7%, and controlled reuse preserves 65% of access alignment and 36% of trench/duct corridors.

Existing capacity: 68 × 1.5 MW = 102 MW. Repowered capacity: 40 × 4.2 MW = 168 MW. Capacity increase: (168 − 102) ÷ 102 = 64.7%. Net annual energy increase: (654 − 290) ÷ 290 = 125.5%. Collection-length reduction: (47.2 − 43.5) ÷ 47.2 = 7.8%.

Pathworks developed a representative full-repower design for an aging Great Plains wind plant: the new 168 MW layout coordinates turbine positions, roads, crane pads, 34.5 kV collection, substation upgrades, demolition and cutover while retaining only the existing assets that meet condition and capacity requirements.

Wind-farm repowering layout strategy showing retired and new turbine positions
Wind-farm repowering layout strategy: fewer, larger turbines reuse the secured site while collection, access and crane logistics are rebuilt around current equipment.
Repowering production result comparing existing and repowered plant capacity and energy
Repowering production result: modeled net annual energy rises from 290 to 654 GWh, an increase of 125.5%, on a 64.7% nameplate-capacity increase.
Electrical and civil reuse controls chart for access, trench and collection assets
Electrical and civil reuse controls: reuse is accepted only where condition, loading, geometry and documentation meet the repower basis — 65% of access alignment and 36% of trench/duct corridor.

Have a similar project?

Send us what you have and we’ll scope it the same way.

Start a Project